The project consists of the design, construction, ownership and operation of a 485MW (net generating capacity after deducting auxiliary electricity consumption) combined cycle gas fired power plant located 31 km north east of Amman in the city of Zarqa Industrial Zone, the Hashemite Kingdom of Jordan (the “project”). The project substitutes Hussein Thermal Power Station, one of the oldest and most inefficient Heavy fuel oil (HFO)–fired power plants in Jordan which was decommissioned in December 2015, with a more efficient power plant.

 

Full Environmental Social Impact Assessment Documentation

Full Stakeholder Engagement Plan

Full  Environmental and Social Action Plan

ACWA Power Zarqa HSSE Policy (English)

ACWA Power Zarqa HSSE Policy (Arabic)

 

KEY FACTS

  • OFFTAKER
    National Electric Power Company (NEPCO)
  • OFFTAKE CONTRACT
    PPA BOO 25 years
  • POWER
    485 MW
  • FUEL
    Natural Gas
  • PROJECT COST
    USD 489 Mn
  • COMMERCIAL OPERATIONAL DATE
    Q3 2018
  • ACWA POWER SHARE
    60.00%
  • EPC
    Shandong Electric Power Construction Corporation III (SEPC III)
  • O&M
    CEGCO (ITSA with NOMAC)
  • PROJECT COMPANY
    Mahatat Al Zarqa Le Tawleed Al Takah Al Kahrabaieyah PSC ("Zarqa")